Revolutionary Base System for Sport, Play & Leisure Areas

The intention is simple. To supply the most versatile base system in the world!

The benefits are significant:

  • to minimize installation time
  • to save money by reducing preparation

What are the issues?

Location

Initially assess the sites suitability, considering the key panel advantages… great drainage, quick installation, temporary or semi permanent installation, minimal base preparation. It should be noted the panels  are less ideal in certain situations where more preparation is required, basically any location where extensive ground works are required – for example very soft ground conditions, split level sites, sites with extreme slopes that need leveling.

Site access needs to be considered for initial site clearance, for sub base preparation, for panel delivery and for carpet installation. How close is lorry access to the point of installation? How wide is the access route? Are there any steps on the access route? Weight limit of the access route surface. The ideal scenario is for Perfect Base panels to be moved by hand from point of delivery to installation location.

Measure the area to be covered with panels. If fitting into an existing space with apparently square corners these should be checked to ensure they are square  as even a small discrepancy can become significant over a long distance and may result in more panels being required or an increase in cut-loss.

Site Preparation

It’s important that the base is solid and stable with consideration given to the height of the finished surface required. To achieve this it may or may not be necessary to remove the natural grass sod. Removal of the natural or existing top surface should be done in a way that maintains a suitable base level. Removal of natural sod to leave a flat level base is difficult for even the most skilled operator so it may be necessary to plan for a 2.5cm – 5cm layer of 0-6mm crushed stone or course sand to be added. This can be compacted, leveled and smoothed using appropriate techniques/equipment for the size of area. The sub base should be firm enough to walk on without leaving distinct footprints and surface deviation should be less than 5mm in 2m

Installing Perfect Base

Measure along the long side of the area to be covered with panels and calculate the number of panels required to cover this edge. Separate this number of panels and prepare them to be trimmed. We refer to this side as the North side. Trim an even 30mm from the male side of all but one of the panels required to go along the north side. Check the NW corner for square corner angle. If square take the first trimmed panel and trim off the other male panel edge an even 30mm. If the corner is less than 90deg again trim 30mm from the remaining male side. If the corner is greater than 90 deg lay out a string line that represents a 90 deg corner and then measure the greatest distance from the string line to the edge of the area to be covered. Add this measurement to the 30mm and then cut this amount from the remaining male side. Spread the first section of heavy grade geotextile along the north edge. Starting in the NW corner place the panel with 2 cut edges leaving 10 mm between the panel and the outside curb. Click together all the pre cut panels along the north edge.

Orientate the last panel to minimize waste and trim to size. Now the north edge should be completed. Start the second row with panel no2 (this panel will not need trimming) place all the other panels to complete row 2 and then measure and cut the 2 end panels. Repeat this process across the whole area. When approaching the last few rows check the orientation of the panels again to minimize cut loss.

Laying Artificial Grass on Perfect Base

We hope this information is helpful, please contact us if you have any questions.


Source link

ASK QUESTIONS

Sponsored Link

Buy Artificial Grass from Manufacturer Directly at Low Price

High-quality artificial grass for garden, playground, football, field hockey, tennis, putting green, and multi-purpose. Located in China and delivers to the world. Minimal quantity 500m². Click to visit the supplier's official website